Chronological progress of HoMerge construction works — foundations, walls, slabs.
HoMerge
2025-11-25
The brick walls of the house are already standing, visible chimneys and preparation of the floor slab with supports. In the foreground, the plot fence.
HoMerge
2025-11-25
Raised gray block walls, and at the top a visible band of red brick, indicating continued brickwork.
HoMerge
2025-12-02
Raised ground-floor walls made of gray blocks and the walls of the upper storey made of light hollow blocks, without a roof; window openings are visible.
HoMerge
2025-12-02
Unfinished house walls with fragments of the ceiling and chimney, wooden scaffolding set against the walls.
HoMerge
2025-12-10
House construction: walls of blocks with window openings and chimneys erected, with protruding reinforcement visible. A worker is standing on the ceiling.
HoMerge
2025-12-10
The ground floor walls have been erected from blocks, and there are fragments of the walls of the higher floor, with the visible slab and reinforcement for further construction.
HoMerge
2025-12-10
The poured ground floor slab and masonry walls made of blocks and hollow bricks are visible, a single-family building under construction.
HoMerge
2025-12-11
View from the car of the construction site: completed foundation and partially erected walls made of blocks. The area is secured with tape; the posts are visible.
HoMerge
2025-12-11
House construction: erected walls and ceiling, visible scaffolding and wooden supports. In front of the building lies construction material on the site.
HoMerge
2025-12-16
Interior of a house under construction with a poured concrete ceiling/floor and walls built from blocks. Scaffolding and preparations for further masonry work are visible.
HoMerge
2025-12-16
Wooden formwork for a reinforced concrete column with protruding rebar, with block walls being erected in the background.
HoMerge
2025-12-16
Raised walls of hollow blocks with formwork for lintels, supported by props. On the first level, scaffolding and the floor slab under construction are visible.
HoMerge
2025-12-16
On the floor slab stand walls made of hollow blocks and the formwork for reinforced concrete columns, with scaffolding beside it. The house construction is at the stage of erecting the walls and preparing the columns.
HoMerge
2025-12-16
At the construction site of a house, walls made of hollow blocks stand up to ground-floor height; formwork and columns are visible. A man on the foundation slab is talking on the phone.
HoMerge
2025-12-16
On the plot there is a large pile of earth from the excavation, next to it lie boards and construction waste.
HoMerge
2025-12-16
On the poured foundation slab stand packaged pallets with blocks; around them lie building materials and tools. Preparation for erecting walls.
HoMerge
2025-12-16
On the poured foundation slab lie construction materials: packages of insulation, blocks, tools and cables, prepared for further work.
HoMerge
2025-12-16
The built walls of blocks and the poured floor slab with a window opening are visible; pallets with construction materials are lying on the slab.
HoMerge
2025-12-16
A poured floor slab with raw walls and window openings; construction materials lie on the slab. A worker and scaffolding can be seen at the construction site.